Industrial procurement

A shared MRO procurement register for multiple sites

Consolidate purchases of identical parts while retaining each site’s quantity, required date and receipt. A register example for checking units and measuring delivery performance.

SOFCONIndustrial procurement
Industrial procurementSeparate product records from demand rows
Practical guide

Separate product records from demand rows

Combining maintenance, repair and operations needs from several sites requires more than joining spreadsheets. The product record holds the full code, revision, approved unit and documents. A demand row holds site, equipment, quantity, required date and recipient. Purchasing can then consolidate the same part while preserving who needs how much and when. Retain the change history for each demand row.

An illustrative unit-normalisation example

The quantities below are illustrative. Do not add kits to pieces until kit contents are confirmed. Even with the same code, verify revision and package contents separately.

Example demand register
Site and demandNormalisation decision
Site A: 2 pieces of an approved partLink to product record and required date
Site B: 3 pieces of the same partAfter compatibility confirmation, purchase 5 pieces; retain separate receipts
Site C: 1 kitKeep a separate row until contents are clarified

Preserve substitution and receipt history

Technical approval of an alternative belongs to a specific product record and application. Approval at one site does not automatically cover the entire fleet. After approval, connect order stages, packaging and receipt documents to the demand rows. Partial delivery should leave the outstanding requirement visible. Where serial or batch identification is needed, add it to the receipt record; a shared delivery-note number does not replace individual product identity.

Measure results against agreed definitions

When evaluating lead time, define its starting event: receipt of an incomplete enquiry or technical approval. Measuring on-time, complete delivery requires requested date, receipt date and open quantity. Track returns caused by incorrect identification separately. Assess savings for the same purchasing scope and comparison period; measure supply reliability against requirements fulfilled by their agreed dates. The register makes the decision, remaining demand and next responsible action visible.